| Location | Activity Description | Unit | Planned Qty | Completed Qty | % Complete | Remarks | | :--- | :--- | :--- | :--- | :--- | :--- | :--- | | | Soil Stack Installation | No. | 8 | 8 | 100% | Pressure test passed | | Level 4 | Rain Water Pipe (RWP) | LM | 120 | 95 | 79% | On track | | Roof | Condensate drain piping | LM | 200 | 140 | 70% | Waiting for HVAC tray alignment | | BOH | Water Heater connection | Set | 2 | 0 | 0% | Starts Oct 25 |

Overall MEP progress is . Key achievements this week: Completion of 4th floor conduit rough-in, start of HVAC duct insulation on floors 2–3. Primary challenge: delayed delivery of VFD panels (expected April 18). mep work progress report sample